Coal-Fired Units to Retire Earlier than Planned

From PowerGenWorldwide.com

11 May 2010– Exelon Power will retire Unit 2 at both the Cromby and Eddystone cosl-fired power plants in Pennsylvania sooner than previously announced because of a revised analysis from the PJM Interconnection.

PJM’s analysis showed that transmission system upgrades can be completed sooner than the original analysis indicated, which will allow the coal-fired units to retire earlier.

PJM determined that Cromby must remain in operation until Dec. 31, 2011, almost a year earlier than planned. The Eddystone unit can remain in operation until Dec. 31, 2012, a full year earlier, to support transmission system reliability.

Exelon announced in 2009 would retire the two units for economic reasons, but agreed to extend operations for system reliability reasons.

Related Articles:

Post Footer automatically generated by Add Post Footer Plugin for wordpress.

This entry was posted in News and tagged , , , , , . Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>